KJ Tait

The Mercers’ Company – Frederick’s Place

Date
19 September 2022

We are approaching the end of our Masterplan of work for the Mercers’ Company at their Home Estate in the City of London.

 

Work on the £26M office and retail development at 4a & 4b Frederick’s Place is now well underway and due for completion in January 2024.

 

MEP packages have just been procured by Knight Harwood and we will have a mock-up of the exposed services section on site under the second floor slab by the start of next year.   A bit of a different look than the City of London is used to!

It is not very often you can say you have been involved in a whole city block regeneration.  We started work in 2014 and completed Phase 1 for Nos 1-3 and 7, 8 & 35 in 2020.

 

To complete our involvement at Frederick’s Place we have now been appointed on the £6.5M townhouse refurbishment at No 4.  This will complete in tandem with 4a & 4b in January 2024.

 

Pictures courtesy of Stanton Williams